Hi there,
Can anyone tell me how to control which days are shaded on the Gannt chart as nonworking times? I'd like to add some holidays to make project delays a little clearer - have been shown how to do this with Calendars on MS Proj, but haven't been able to replicate on Plan and unsure if it's not a feature or if I'm just looking in the wrong menus... Thanks! |
Registered Member
|
Not a feature I'm afraid.
It just takes the nonworking days from the system locale. |