Registered Member
|
Hi
I move from old KDE into a new one, and now I have a problem with Kplato. After adding a new task (or changing a new one) I can not see those changes on the Gantt View. It used to be a button calculate (which used to work perfectly well in the old version), but I can not find it anymore. What to do now? Downgrade to the previous version or is there any solution? |
Registered Member
|
in editors, go to schedules, then add schedule, then you click on calculate
best regards
djouallah, proud to be a member of KDE forums since 2008-Oct.
|